Budget
$88,000
Workforce
4
Time Line
3 weeks

The project scope consisted of the design of the outdoor area to allow for the maximisation of the space, earthworks, playground equipment and the supply & installation of new hardscaping and soft-scaping to create a safe play area for pre-school children.  To complete the project some playground equipment was re-installed.

Hardy Landscaping team commenced with the removal of existing sand pits, lawns, bike paths, gardens and followed the design for the supply and installation of the new hardscaping and soft scaping. Existing playground structures were removed, and earthworks cleared and levelled the site in preparation for the supply of new soil, textured concretes, rubber soft-fall, grass and shade sails.

Site safety and WHS procedures were applied and the project was completed and delivered on time and budget without any incidents.